A typical message our rental desk gets on a Sunday morning: “Method statement came back Code C. Consultant wants the crane load chart, outrigger loads and the third party certificate. Can you send them today? We mobilise Wednesday.” A method statement rejected by the consultant is not the end of the job. It is a list of what to fix.
In that kind of call, the engineer has usually done the hard part. The sequence, the risk assessment and the permits are ready. What sank it was the page about the machine, written before anyone confirmed which crane was coming to a tower in Business Bay.
We are not consultants and will not tell you how to argue with one. We do see the equipment side of these returns every week. Below: what the review codes mean, why consultants send documents back, a resubmission process, and the machine documents that close most lifting comments.
What should you do first when a method statement is rejected?
Do not start the work. Read the consultant’s code and every comment, sort comments into paperwork, site-specific and technical items, then fix them inside a new revision of the method statement and risk assessment. Add a comment response sheet showing where each comment is closed, attach missing certificates and resubmit the full package.
A method statement rejected on a Dubai project can feel personal, especially with a project manager asking for dates. It rarely is. The consultant’s job is to protect the client and the people on site, and each comment points to something they could not find in your document.
Consultant review also does not move responsibility away from you. Even after approval, the contractor still owns the method, the risk assessment and how the work is done. That is why a careful revision is worth the extra day.
What do Code A, B, C and D mean on a returned method statement?
Most Dubai projects stamp returned submittals with a letter code. Wording changes between consultants and contracts, so check the code key on your own submittal stamp or in the project’s document control procedure. The table shows common usage, not a rule.
| Code (common usage) | Typical wording | Can you start the activity? |
| Code A | Approved / No objection | Yes, as submitted |
| Code B | Approved as noted / Approved with comments | Usually, but only by following every note; some projects want a revised copy first |
| Code C | Revise and resubmit | No. A full new review cycle starts |
| Code D | Rejected / Not approved | No. Usually a new submission is needed |
Code C is the most common way to see a method statement rejected. The method statement Code C resubmit cycle starts again from zero. Code D usually signals a more basic problem, such as the wrong method or the wrong machine for the task.
Why do Dubai consultants get a method statement rejected?
These are the reasons we hear about most from the contractors we supply. They are common patterns, not statistics, and most have a clear fix.
Method statement rejected? The 12 most common reasons and what fixes them
| Reason | What the consultant wants to see | Who usually supplies it |
| Generic or copied from another project | Project name, plot, access route, working hours, named supervisor, site hazards | Contractor |
| Method and risk assessment do not match | Every hazard has a control; every activity appears in both | Contractor HSE |
| Controls are PPE only | Hierarchy of controls applied, removing the hazard first | Contractor HSE |
| No named competent persons | Supervisor, lifting supervisor, operator, rigger, signalman with certificates | Contractor, plus rental company for supplied operators |
| Operator or rigger certificates missing or expired | EIAC accredited third party certificates, IPAF PAL cards for MEWPs | Contractor or rental company |
| Machine certificate missing or expired | Current third party certificate for the machine | Rental company |
| No lift plan for crane work | Load weight, radius, crane configuration, load chart extract, rigging, exclusion zone | Contractor with rental company data |
| No ground bearing or outrigger check | Outrigger loads, pad sizes, ground or slab capacity check | Rental company data plus contractor or engineer |
| MEWP work without a rescue plan | Rescue plan, trained ground person, emergency lowering procedure | Contractor, with machine data from rental company |
| Emergency arrangements not site specific | Nearest hospital, first aider, assembly point, emergency numbers | Contractor |
| Conflicts with site rules or permits | Permit to work references, hours, midday break, community rules | Contractor |
| No revision control or sign-off | Revision number, date, change log, correct signatures | Contractor document control |
Look at the third column. Several of the hardest comments are closed with documents held by your equipment supplier. Where operator competency is the gap, see our guide for when you cannot source an IPAF certified operator.
Why do equipment pages cause so many lifting plan rejections?
When contractors send us a Code C, the equipment comments were usually written before anyone confirmed which crane was coming. The crane size, radius and outrigger loads were guesses, and a consultant spots a guess quickly.
The second pattern is a mismatch: the approved document names one machine and a different one turns up. If radius is the real issue, read what happens when a crane cannot reach the required radius.
How do you fix a method statement rejected by the consultant, step by step?
This process works for a crane lift, a MEWP task or an excavation.
Step 1: Stop and log the return
Record the code, date returned and reviewer in your submittal register. Do not mobilise for that activity. Accurate dates matter if the programme is questioned later.
Step 2: Read every comment and sort it into three buckets
Paperwork (signatures, revision), site specifics (location, emergency, permits) and technical (sequence, lifting, equipment, temporary works).
That Sunday contractor had around twenty comments. Once sorted, paperwork and site items went to the engineer and HSE officer. The equipment and lifting bucket was the one our desk could help close within a day, because the answers were machine data.
Step 3: Ask questions before you rewrite
If a comment is unclear, or two comments conflict, ask the reviewer for a short call. Agree the meaning, then confirm it in writing.
Step 4: Collect the missing attachments
Equipment data and certificates from your rental company, operator and rigger cards, the lift plan, ground information and the rescue plan. Check every expiry date on the day you submit.
Step 5: Fix the document, not the email
Make every change inside the method statement and risk assessment. Cloud the changes and raise the revision number. Answers sent only by email are not part of the package the reviewer checks.
Step 6: Write a comment response sheet
List the comment number, the comment, your response, and the section and page where it is closed. It is the most useful page in a resubmission.
Step 7: Resubmit the full package and follow up
One transmittal, response sheet first, every attachment included. No single review period applies to every Dubai project, so check your contract and follow up politely when it is due.
What does a comment response sheet look like?
Here is a short example built from the crane comments in our opening story.
| No. | Consultant comment | Our response | Where closed |
| 1 | Provide crane load chart for the proposed configuration | Load chart extract for the configuration and radius attached | Appendix C, page 2 |
| 2 | Provide outrigger loads and ground bearing check | Outrigger data from supplier attached; ground check by site engineer included | Section 6.3, Appendix D |
| 3 | Operator and rigger certificates not attached | Third party certificates attached, all in date | Appendix E |
| 4 | Emergency arrangements not site specific | Nearest hospital, assembly point and first aider added | Section 9 |
Which equipment documents should you attach to a Dubai method statement?
Ask your supplier for these items before you write the equipment section.
Mobile crane and spider crane
- Crane model and configuration for the lift
- Load chart extract, lift radius and lift height
- Outrigger loads and pad sizes
- Current third party certificate for the crane and lifting accessories
- Operator, rigger and signalman third party certificates
Dubai Municipality’s lifting equipment examination and certification guideline sets the rules these papers must meet. For machines, see mobile crane rental in Dubai and our note on hired crane certificates.
Boom lift, scissor lift, spider lift and man lift
- Model, working height, outreach and platform capacity
- Six month third party inspection report
- Operator PAL card and training record
- Rescue plan and the machine’s emergency lowering procedure
- Harness and lanyard requirements for boom work
A MEWP method without a rescue plan is one of the most predictable returns. Machines include boom lift rental, scissor lift rental in Dubai and spider lift rental. For competency evidence, see IPAF training in Dubai.
Telehandler and forklift
- Model, capacity chart and attachments
- Current third party certificate
- Operator third party certificate (forklifts are named in the Dubai Municipality lifting guideline)
See telehandler and boom loader rental.
Excavators, backhoe loaders, bobcats and compaction plant
- Model, operating weight and attachments
- Service and inspection records
- Operator competency evidence
- Method for clearing underground services before digging
For smaller digs, see mini excavator rental.
How does a “documents for the method statement” request work at our rental desk?
When the Sunday message comes in, we start with questions. What does the load weigh? What radius and lift height? What is the ground or slab? How wide is the access and how high is the gate?
Then the timing. What date and hours, and are there permit limits? Will the operator be ours or yours? Those answers become the equipment section of the method statement.
We propose a machine that fits, and you can ask our desk which data sheets, certificate copies and operator documents are available for that machine and your dates.
The honest boundary: Dream Way supplies machines, their data and trained operators on request. The contractor or its engineer owns the method statement, ground assessment and any temporary works design.
Method statement bounced on the equipment comments? Send our rental desk the lift details and the consultant’s comments on WhatsApp +971 56 857 8181 or call 056 857 8181. We will tell you which machine fits and what documents go with it, or reach us through our contact page.
What Dubai rules should your method statement reflect?
Consultants read method statements against local requirements.
Dubai Municipality risk assessment guideline
DM-HSD-GU137-RA2 (Version 1.0, issued 17/02/2025) says employers with five or more employees must record hazards, people at risk and control measures. Controls are reviewed when they stop working, after accidents, when near misses recur or when changes bring new risks.
It recommends a simple 3×3 matrix, and its hierarchy of controls starts by asking whether the hazard can be removed. That is why PPE-only risk assessments get sent back.
Lifting equipment and operator certification
DM-HSD-GU48-ECLA2 (Version 5.0, issued 29/01/2025) requires cranes, hoists, lifting gear and forklifts to be certified by an EIAC accredited third party every 12 months, with the certificate kept on site. Operators, riggers and signalpersons need EIAC accredited third party certification too.
MEWP work and the rescue plan
The Dubai Municipality MEWP guideline DM-HSD-GU67-MEWP2 (Version 2.0, issued 06/09/2024) asks for a risk assessment by a competent person and a rescue plan so a trapped person can be recovered safely and quickly.
A trained person must be at ground level while the risk exists. Training is repeated at least every two years, and MEWPs are inspected every six months by an EIAC accredited third party.
Free zones and developer communities
Trakhees Safety Alert 029, for PCFC areas such as Jebel Ali, calls for a lifting plan for crane lifts and approved third party sign-off on cast-in lifting lugs. In DDA communities, Circular 339 on Safe Work at Height (12 December 2019) holds consultants and contractors responsible for compliance. Check your zone before you submit.
Working hours, heat and weather
Your method should match the hours you can actually work. Plan around the midday break rules, a night work permit where needed, and sandstorm limits for cranes and MEWPs.
Can you start work under “approved as noted”?
Usually, but only by following every note. Approved as noted is not a clean approval. Some consultants want a revised copy first. Ignoring the notes can put the approval at risk. If unsure, ask in writing and keep the reply.
An approved as noted method statement still carries conditions. Brief the site team on every note before work starts, so what happens on site matches what the consultant accepted.
Mistakes to avoid when resubmitting a method statement rejected once
- Answering comments in an email instead of the revised document
- Changing things the consultant did not ask about without flagging them
- Keeping the same revision number
- Naming equipment before confirming it with the supplier
- Attaching certificates that have expired by submission day
- Arguing in writing before asking for a call
- Starting on a Code C because “it is only paperwork”
- Swapping the crane or MEWP after approval without a revision
A new machine means a new load chart, new outrigger loads and new certificates, so the method needs a revision too.
How do you get the next method statement approved first time?
Confirm the equipment and collect its documents before drafting. Use a site-specific checklist for location, emergency arrangements, permits and hours. Cross check the method against the risk assessment line by line.
For heavy lifts or work over public areas, ask the consultant for a short pre-submission meeting. Keep a library of in-date certificates for each machine and person.
As for the Sunday message, what usually happens next is simple. One clean revision goes in with a response sheet, the equipment comments are closed with real data, and it comes back approved or approved as noted.
The lesson most engineers take from it: ask for the machine documents before writing the method statement, not after it bounces.
Method statement rejected? Frequently asked questions
Why do consultants reject method statements in Dubai?
Common causes are generic content copied from other projects, a risk assessment that does not match the method, missing competency certificates, expired machine certificates, no lift plan or ground check for cranes, and no rescue plan for MEWP work.
What does Code C mean on a method statement?
On many Dubai projects Code C means “revise and resubmit”. You cannot start that activity. Answer every comment in a new revision and resubmit for a fresh review. Check your project’s code key, because wording varies.
Can I start work if my method statement is approved as noted?
Usually only by following every note, and some consultants want a revised copy first. If unsure, ask in writing. Treating approved as noted like a clean approval is a common way to fail a later site inspection.
What is the difference between a method statement and a risk assessment?
The method statement explains how the work is done, with people, equipment and sequence. The risk assessment records hazards, who is at risk and the controls. A submission is often rejected when the two do not match.
What should a crane method statement include in Dubai?
Crane model and configuration, load weight, radius and height, a load chart extract, outrigger loads and ground check, rigging, exclusion zone, a named lifting supervisor, certified operator, rigger and signalman, the crane’s current third party certificate and emergency arrangements.
Do I need a rescue plan in a MEWP method statement?
Yes. Dubai Municipality’s MEWP guideline requires a rescue plan so a trapped person can be recovered safely and quickly, with a trained person at ground level while the risk exists.
Does Dubai Municipality approve method statements?
On most building projects the consultant and main contractor review the method statement; it is not filed with Dubai Municipality. Dubai Municipality sets the safety requirements it must meet, and some zones need separate permits.
What if the consultant’s comments are all about equipment?
Ask your rental company for the machine data, certificates and operator documents, and check with our desk what is available for your machine and dates. The contractor still owns the method statement and any ground or temporary works assessment.
Get the equipment side of your method statement right first time
If your method statement keeps coming back on crane, MEWP or plant comments, start with the machine. Tell our rental desk the load, radius, height and site. We will propose the right crane, boom lift, scissor lift, spider lift, telehandler or excavator, with trained and certified operators on request.