The sky turns orange brown. The far towers disappear. The radio crackles, and the banksman can no longer see the crane cab.

Every dust season, sandstorm crane and MEWP work disruptions hit UAE sites. Lifts stop halfway through rigging. Crews are caught at height on exposed facades. The crews who come through it well are not the lucky ones. They are the ones with a simple plan.

This guide gives you that plan: what to do with cranes and MEWPs when the dust arrives, the numbers that actually matter, and how to restart safely once it clears.

What should you do when a sandstorm hits during crane or MEWP work?

When a sandstorm hits, stop new lifts, land any suspended load under control and lower and stow MEWPs. Put the crane in the out of service condition its manual describes, shut down and move everyone to shelter. Restart only when wind and visibility are back within limits and each machine has been walked round and checked.

There are three stop triggers. The manufacturer wind limit, found in the crane’s load chart and on the MEWP data plate. A loss of clear sight or reliable communication between operator and signaller. And your site’s own weather plan.

National Center of Meteorology (NCM) alerts are the early warning. The decision comes from those three triggers.

A dusty afternoon on our rental desk

A contractor running a mobile crane and two boom lifts on a warehouse extension near Jebel Ali called our desk as a dust front came in.

The site supervisor had two questions, and both were urgent.

The crane crew were rigging a lift. Should they finish it before the dust arrived? And the boom crew were already halfway up the cladding. What should they do?

We gave the same answer we always give in that moment.

Do not start the lift. If it is not in the air yet, it stays on the ground. Anything already lifted gets landed, under control, at the nearest safe point.

Bring both booms down and stow them. Do not try to finish the panel.

For the crane, slew and park it the way its manual describes for those conditions, then shut it down. Get everyone into shelter and count heads.

And when it clears, call us. We will talk through the checks before anything goes back up.

The supervisor did exactly that. The crews waited it out in the site cabin.

When the wind dropped and the far side of the site was visible again, the operators wiped down glass and controls, walked round each machine and ran function tests. Once wind and visibility were back within limits, they restarted with light work first.

An ordinary afternoon, handled calmly. That is what a good plan looks like.

Crane and MEWPs stowed during sandstorm on UAE construction site

Why a sandstorm stops crane and MEWP work: three separate problems

A sandstorm is not one hazard. It is several at once, and each one can stop lifting work on its own.

Wind and gusts push past the machine’s limit

For MEWPs, outdoor rated machines are typically rated for a maximum wind speed of 12.5 m/s, which is about 45 km/h or 28 mph, according to IPAF. Always use the figure on the plate of the actual machine. Some carry a lower rating.

For cranes, there is no single figure. The maximum permissible wind speed is in the crane’s own load chart, and it depends on the configuration and the load. Liebherr explains that the gust is measured as a 3 second average at the maximum hoisting height.

Two things catch people out.

First, wind at height is stronger than wind at ground level, and forecasts are usually given for 10 metres above the ground.

Second, NCM dust alerts usually quote wind and gusts in km/h, while plates and load charts often use m/s. Convert before you compare. To turn m/s into km/h, multiply by 3.6.

If wind on a tower facade is your main worry, see our guide on what to do when wind speed exceeds the MEWP limit on a Dubai tower.

Visibility drops and signalling breaks down

Lifting depends on sight. The operator has to see the load, the landing area and the signaller, or have communication that can be relied on completely.

When dust takes that away, the lift stops. It does not matter if the wind is within limits.

NCM alerts during dust events often report horizontal visibility falling below 2,000 or 1,500 metres in places. On a busy site, between buildings and stacked materials, it can be far worse locally. A blind lift is never acceptable.

Dust gets into machines and onto surfaces

Fine dust settles everywhere. On controls, steps, platform floors and windscreens. It can also get into air intakes.

That is why a restart is never just “turn the key”. Controls need wiping, glass needs cleaning, filter indicators need checking and functions need testing. Dust can also hide problems that a quick look would normally catch.

Loose material becomes a projectile

Sheets, insulation, packaging and light panels on slabs and in baskets can all be lifted by strong wind. Secure them or remove them before the storm, and keep people out of any drop zone.

How to read NCM dust and wind alerts for site decisions

The National Center of Meteorology issues dust and wind alerts across the UAE. It also runs a warnings map and the Weather UAE HD app.

Alerts usually state expected wind speeds and gusts in km/h, and visibility in metres. That is useful, but it is not a site decision on its own.

Here is how we suggest using them:

Authorities do act on severe weather too. In 2018, for example, Abu Dhabi City Municipality ordered an urgent stop to crane lifting operations and work at height during a spell of rough weather. That was a specific instruction for a specific event, not a standing rule, but it shows how seriously the risk is taken.

Step by step: what to do with cranes when a sandstorm arrives

  1. Do not start a new lift (appointed person or lift supervisor). Once a dust front is forecast or visible, no new lift begins. If rigging is underway, stop and secure what you have.
  2. Land any suspended load under control (operator and signaller). If a load is already in the air, bring it down to the nearest safe landing point, smoothly. Do not rush it, and keep the signaller in clear contact.
  3. Unhook or secure the load and clear the area (rigging crew). Make the load safe on the ground. Clear everyone from under and around the crane and its swing path.
  4. Put the crane in its out of service condition (operator, with the manual). Follow the manufacturer’s instructions for the configuration and the forecast. That may mean retracting or lowering the boom. Liebherr’s guidance is clear that when limits are exceeded, crane operation stops and the boom is set down as the manufacturer instructs.
  5. Shut down and secure (operator). Switch off, close the cab and secure loose items around the machine.
  6. Move everyone to shelter (supervisor). Get the whole crew to shelter and confirm the headcount by radio.
  7. Log it (supervisor). Record the time, the reason for stopping and the conditions.

One more point. A crane’s load moment limiter does not protect you from side wind. Liebherr notes that it does not detect side wind loading. So do not rely on it to warn you.

If you hire cranes for this kind of work, our mobile crane rental in Dubai team can talk through wind limits for the configuration you need. The same thinking applies to a boom loader, which also lifts loads at height and is affected by wind.

Mobile crane vs tower crane: a quick note

This guide focuses on hired mobile cranes. Tower cranes have their own out of service procedures set by the manufacturer and the site. Follow those, not this list.

Step by step: what to do with MEWPs when a sandstorm arrives

  1. Stop the task and secure the basket (operator). Put tools away. Secure or remove materials in the basket. Do not try to fit one more panel.
  2. Lower and retract to the stowed position (operator). Bring the platform down smoothly, keeping clear of the facade. Retract fully to the stowed position.
  3. Move to a sheltered, firm spot if safe (operator). If the manual allows and it is safe to travel, drive to a sheltered spot on firm ground. Otherwise, leave the machine stowed where it is.
  4. Switch off and secure (operator). Switch off, remove the key, and close covers on control boxes where they are fitted.
  5. Get to shelter (everyone). The operator and the ground crew go to shelter together.
  6. If a platform cannot be lowered, follow the rescue plan (supervisor). Use the ground controls as the manual describes, follow your site rescue plan, and call the rental company straight away.

For machines suited to exposed facade work, see our boom lift rental Dubai range.

Crew moving to shelter during sandstorm disrupting lifting work UAE

How to restart safely after the sandstorm

Wait for wind and visibility to come back within limits

Check the latest NCM update. Take readings at platform or hook height where possible. And confirm that the operator and the signaller can see each other and the landing zone clearly.

If any of those are not right, wait.

Walk round, clean and check

Dust hides problems. Before anything lifts:

Brief the crew again and restart in stages

Hold a short toolbox talk. Start with light lifts or low level work rather than the heaviest job of the day. And keep an eye on the forecast, because a second wave of dust is common.

When to call the rental company

Call us if you see warning lights, hear unusual noises, or notice controls not responding normally. The same goes for filter warnings, any sign of impact or damage, or simply a crew that is not comfortable with the machine.

Our 24/7 on site support is there for exactly this. If a unit has a problem, we arrange a machine swap. You can call our rental desk any time.

As we tell crews after a dusty day: “After a sandstorm, the extra ten minutes your operator spends on a walk round is the cheapest part of the day.”

Practical example: a facade crew on a coastal tower

Picture a MEWP crew working on the upper facade of a coastal tower.

During the morning, NCM issues a dust alert for the area. It mentions gusts reaching into the mid range of the 40s in km/h.

The supervisor does the conversion. The machine plate says 12.5 m/s, which is 45 km/h. The forecast gusts are already near that figure. And gusts at the height the crew is working will be stronger than the 10 metre forecast.

So the supervisor does not wait for the dust to arrive. The crew is stood down before the front comes in. The platform is lowered and stowed, and the crew switches to ground level prep work.

After the storm passes, the readings drop and hold. The operator walks round the machine, cleans the controls, runs the checks, and the crew goes back up.

No drama. Just a decision made early, from the right numbers.

Dust season checklist for sandstorm crane and MEWP work

Run through this at the start of the season:

Dust season overlaps with peak summer heat. Our guide on what to do when summer heat halts operator work on a Dubai site covers the midday break side of the season.

Frequently asked questions

Should cranes stop during a sandstorm?

Yes, when wind exceeds the limit in that crane’s load chart, or when the operator cannot clearly see the load, the landing area and the signaller. Land any suspended load under control, put the crane in its out of service condition as the manual describes, shut down and move the crew to shelter.

What wind speed stops crane work?

There is no single figure. The maximum permissible wind speed is set in each crane’s load chart, and it depends on the configuration and the load. Gusts are measured as a 3 second average at hoisting height, and wind at height is usually stronger than the 10 metre forecast.

Can a boom lift be used in a dust storm?

Not when wind exceeds the plate value, which is typically 12.5 m/s, or about 45 km/h, for outdoor rated machines. Poor visibility is also a reason to stop. Lower the platform, retract to the stowed position, switch off and get the crew to shelter until conditions are back within limits.

What does an NCM dust alert mean for my site?

Treat it as an early warning to review planned lifts and all work at height. Alerts usually give wind and gust speeds in km/h and visibility in metres. Make the actual stop decision from your own values, based on the crane load chart, the MEWP plate and readings taken at height.

What should we check after a sandstorm?

Clean windscreens, mirrors, cameras and controls, and clear dust from steps and platforms. Check air intake and filter indicators as the manual describes. Test lights, horn, alarms, emergency stops and all functions from the ground and platform, and check the ground under outriggers.

When is sandstorm season in the UAE?

The summer shamal winds typically run from around late May to mid August, according to NASA. They are hot, dry and northwesterly, and strong enough to lift dust and cut visibility. Dust events can also happen outside this period, so keep checking NCM alerts all year.

Can Dream Way help after a storm?

Yes. We offer 24/7 on site support for machines on hire with us, and if a unit has a problem after a storm, we arrange a machine swap. Call our desk if you see warning lights, unusual noises, controls not responding normally or any damage.

Need support before or after a sandstorm? Talk to Dream Way

We pick up the phone when the weather turns.

We supply mobile cranes from 25 to 500 tons, boom lifts, man lifts, scissor lifts and spider lifts, with IPAF trained operators on request. Every machine is checked before it leaves our Ras Al Khor yard, and our 24/7 on site support includes a machine swap if a unit has a problem. We deliver across all seven Emirates. See our wider heavy equipment rental across the UAE.

Call 056 857 8181 or 054 581 9331, message us on WhatsApp, email sales@dreamwayrental.com, or call our rental desk through our contact page.

Leave a Reply

Your email address will not be published. Required fields are marked *